As a result of the clubs decision to seek promotion this season further development of the ground is planned for the coming weeks.
To ensure we have the best possible chance of meeting the ground grading criteria for the Evo-Stick League the following activities will be taking place;
1) Repairs to the pitch perimeter
2) Modifications to the Surrey St boundary wall
3) Installation of a back section on the Surrey St covered stand
4) Modifications to the covered seating
5) Installation of 'press' facilities
6) Upgrading the First Aid facilities
7) Upgrading the hygiene facilities in public areas
The majority of the work is planned for the 10 day window we have following the home game with Alsager on Saturday the 18th of February.
Surrey Street Development Blog
surreystreetdevelopment@googlemail.com
Tuesday, 14 February 2012
Friday, 12 August 2011
Almost there
Saturday saw the 1st home game of the 2011-12 season and Glossop North End supporters got the chance to see their new facilities at first hand.
Whilst there are still a few tasks to be completed the majority of the work has been completed, a great achievement in just 12 weeks.
Below are a few photo's but the best way to appreciate the work is to come down to Surrey Street and see it for yourself.
Whilst there are still a few tasks to be completed the majority of the work has been completed, a great achievement in just 12 weeks.
Below are a few photo's but the best way to appreciate the work is to come down to Surrey Street and see it for yourself.
Wednesday, 22 June 2011
The Clubhouse gets a roof!
6 weeks into the project and the clubhouse now has a roof as well as roller shutters. The installation of the electrics and plumbing is now underway.
Work is also continuing on the changing rooms.
In addition to the building work the pitch renovation is almost complete, the walkway behind the top goal has been moved back and the land behind the goal has been completely levelled and seeded.
Thursday, 26 May 2011
Project Update
The first 4 weeks of the project have flown by and good progress has been made on both the changing rooms and the clubhouse. GNE photographer Jim Lockwood has been posting regular updates on the clubs messageboard and his photo's can be found by clicking the link below.
Project Photo's
Wednesday, 4 May 2011
Tuesday, 3 May 2011
Building work begins
Following Glossop North Ends final home game of the season yesterday, work has begun on the new clubhouse and changing rooms.
The project is expected to take 10 weeks and be completed in time for the start of the 2011-12 season.
Progress will be posted at all major stages of the build.
The project is expected to take 10 weeks and be completed in time for the start of the 2011-12 season.
Progress will be posted at all major stages of the build.
Thursday, 24 March 2011
New Changing Room & Clubhouse Take Shape
Below is a copy of the proposed layout of the new Glossop North End Clubhouse and Changing Rooms.
The new facility will provide;
Improved disabled access
40% bigger clubhouse
50% bigger changing rooms
Separate female official changing room
Improved First Aid facilities
Work will commence on Tuesday 3rd May and is estimated to take 8 weeks.
The new facility will provide;
Improved disabled access
40% bigger clubhouse
50% bigger changing rooms
Separate female official changing room
Improved First Aid facilities
Work will commence on Tuesday 3rd May and is estimated to take 8 weeks.
Monday, 28 February 2011
New Surrey Street Stand is complete!
Glossop North Ends new Surrey Street stand is now complete.
More good news is the fact that, despite the extra groundwork that had to be carried out and the delays caused by the weather, the project came in on budget.
Pictured above with the stand are Development Team Members Stewart Taylor and Neil Rimmer.
The next stage of the development is to install new access gates and to move the turnstiles further up Surrey Street. All the materials for this next step have been kindly donated by Spire Construction (NW) Ltd. and Travis Perkins.
More good news is the fact that, despite the extra groundwork that had to be carried out and the delays caused by the weather, the project came in on budget.
Pictured above with the stand are Development Team Members Stewart Taylor and Neil Rimmer.
The next stage of the development is to install new access gates and to move the turnstiles further up Surrey Street. All the materials for this next step have been kindly donated by Spire Construction (NW) Ltd. and Travis Perkins.
Tuesday, 30 November 2010
New Surrey Street stand rises above the weather!
Tuesday, 9 November 2010
Piling work begins
Despite the best attempts of the Glossop weather, piling has begun for the new Surrey Street stand. The work is expected to be completed by the end of the week after which the concrete base can be laid.
Although the steelwork is already on site it needs fabricating and there are a few items still awaiting delivery.
We are still confident of having the stand finished in time for the next home league game, which is Colne on the 27th of this month.