6 weeks into the project and the clubhouse now has a roof as well as roller shutters. The installation of the electrics and plumbing is now underway.
Work is also continuing on the changing rooms.
In addition to the building work the pitch renovation is almost complete, the walkway behind the top goal has been moved back and the land behind the goal has been completely levelled and seeded.